// THE QUOTE

i'll give you an example with the george i had the construction permit and we broke ground about two days after

Concrete war story on stacking/overlapping phases and the risk of breaking ground two days after the permit, landing on why waiting would add years. Stands fully alone.

Full episode at 39:56How Halifax's Dexel Developments Builds Landmark Apartments: Vertical Integration, BIM, and 25-Year CapEx Thinking
Share
THE LESSON THIS CLIP CARRIES
Stack approvals and construction phases in parallel; waiting for each step to finish before starting the next doubles timelines.
if you waited for each step to be finished before you started the next, the George would still be another 10 years away
More lessons like this ▸
THE CHAPTER IT LIVES IN
BIM, design collaboration, and the Press Block
31:10
Clips like this, every two weeks.
SOURCE: 39:56 of How Halifax's Dexel Developments Builds Landmark Apartments: Vertical Integration, BIM, and 25-Year CapEx Thinking