// THE QUOTE
“in the city of Mount Pearl we did a major water and sewer project with the design build methodology”
— Terry Hussey
Concrete named project: first design-build water/sewer in NL, a full year faster than bid-build; credible innovation story with a takeaway for municipalities.
Full episode at 1:11:10How to Save $1M on Your Next Construction Project — Owner’s Rep, Cost Estimating & Design-Build | Terry Hussey, Vigilant Atlantic ▸
THE LESSON THIS CLIP CARRIES
Design-build delivery for infrastructure projects can achieve a one-year schedule advantage over traditional design-bid-build without significant cost premium; piloting it alongside a traditional project simultaneously is a rigorous way to prove the value.
“it was a year faster than the traditional model in terms of getting that infrastructure into the ground”